New Jersey’s Environmental Justice (EJ) Rules require certain regulated facilities in overburdened communities (OBCs) to assess their potential environmental and public health impacts. Under N.J.A.C. 7:1C, affected applicants must examine the potential effects of their proposed activities on surrounding communities and meet the state’s environmental justice requirements before the New Jersey Department of Environmental Protection (NJDEP) makes its permitting decision.
Understanding these requirements helps facility owners prepare the necessary documentation, address community concerns, and navigate the permitting process. The following steps outline how regulated facilities can prepare for NJDEP’s environmental justice review.
Step 1: Determine Whether the Facility Is Subject to the EJ Rules
The first step is determining whether the facility and proposed permit action fall within the regulations. NJDEP’s EJ Rules do not apply to every regulated property. They cover specified facility categories and certain permit applications involving overburdened communities.
These include major sources of air pollution, resource recovery facilities, large sewage treatment plants, and certain solid waste facilities. Applicable permit actions may involve new facilities, expansions, and renewals of major source operating permits.
Facility owners should review their permit type, proposed activities, and property location. NJDEP’s Environmental Justice Mapping, Assessment and Protection (EJMAP) tool helps identify whether a site is within an OBC and provides information about surrounding environmental conditions.
However, being located within an OBC does not automatically make every permit application subject to the rules. Applicants must verify that both the facility category and proposed permit action meet the regulatory criteria.
Step 2: Review NJDEP’s Initial Screening Information
Once it is determined the rules apply to the facility, applicants must examine the environmental and public health stressors affecting the surrounding community.
NJDEP provides initial screening information that identifies relevant pollution sources, environmental indicators, and community conditions. Applicants should review these findings alongside available site-specific information to determine which concerns require further assessment.
For example, an industrial facility may need to evaluate its air emissions alongside nearby traffic-related pollution and emissions from other industrial operations.
This assessment must consider cumulative conditions rather than examining the proposed facility as an isolated pollution source. Understanding existing environmental burdens also helps applicants identify which impacts may require mitigation.
Step 3: Prepare the Environmental Justice Impact Statement
Following the initial screening, the applicant must prepare an Environmental Justice Impact Statement (EJIS) in accordance with N.J.A.C. 7:1C-3.2. The statement must address the proposed project’s potential effects on the surrounding community and cover the following components:
- Executive Summary– An overview of the facility, proposed activities, and assessment findings.
- Community and Site Description– Information about nearby residences and sensitive receptors, community demographics, zoning, and physical characteristics.
- Facility Operations– Details about existing and proposed activities, equipment, operating hours, staffing level, traffic routes, and pollution controls.
- Permit Inventory– A list of required federal, state, and local permits for construction and operation.
- Initial Screening Results– NJDEP’s findings on relevant environmental and public health stressors.
- Impact Assessment– An evaluation of potential positive and negative impacts during site preparation, construction, and operation.
- Public Participation Plan– Proposed notification methods, hearing arrangements, and opportunities for community feedback.
- Impact Avoidance Measures– An explanation of proposed measures to avoid or minimize disproportionate impacts, including engineering controls and operational changes.
The impact assessment requires particular attention because applicants must examine conditions under maximum facility usage or output. Applicants should identify relevant pollutants, estimate their quantities and concentrations, and describe potential exposure pathways to help NJDEP evaluate how emissions, discharges, traffic, and other facility activities could affect existing environmental and public health conditions.
Technical reports can provide supporting evidence for the EJIS. Applicants should summarize the relevant findings, identify the corresponding sections and page numbers, and include clear cross-references to help NJDEP locate the supporting information.
Step 4: Determine Whether Supplemental Information Is Required
Under N.J.A.C. 7:1C-3.3, some applications require additional technical assessments if the surrounding community experiences adverse cumulative stressors or if NJDEP needs further information to evaluate the facility’s contribution.
Depending on the project, supplemental documentation may include:
- Site maps showing topography, drainage, wetlands, and nearby water bodies.
- Investigations of existing soil and groundwater contamination.
- Localized air quality assessments.
- Flooding, stormwater, and climate change evaluations.
- Traffic and transportation studies.
- Sewage collection, treatment, and water supply information.
- Noise, odor, and dust assessments.
- Energy demand and proposed pollution control measures.
- Relevant facility compliance history and enforcement actions over the preceding five years.
Applicants must also evaluate feasible control measures to reduce the facility’s contribution to environmental and public health stressors. For example, facilities with substantial truck activity may need to assess traffic patterns, vehicle emissions, and alternative routes. Sites with stormwater concerns may require improved drainage or additional treatment controls.
Each assessment should connect identified risks to practical mitigation measures. Simply listing potential problems without explaining how the facility intends to address them will not adequately support NJDEP’s review.
Step 5: Submit the EJIS for Administrative Review
After completing the EJIS and required supplemental assessments, applicants must submit the documents to NJDEP for administrative review.
Under N.J.A.C. 7:1C-3.4, NJDEP generally has 10 days after receiving the submission to request revisions or additional information, or to authorize the applicant to proceed with public participation.
Applicants should not begin formal public notification before receiving authorization. If NJDEP identifies deficiencies, the applicant must revise the documents and provide the requested information.
Working with an experienced NJDEP permit consultant can help facilities coordinate technical reports, review documentation, and identify missing information before submission.
Step 6: Conduct the Public Participation Process
Once NJDEP authorizes the applicant to proceed, the facility must complete the required public notification and hearing procedures pursuant to N.J.A.C. 7:1C-4. The notification process must begin at least 60 days before the public hearing, and applicants must:
- Provide a copy of the EJIS to the clerk of the municipality where the OBC is located.
- Publish hearing notices in at least two newspapers circulating within the community. At least one must be a local non-English-language newspaper when applicable.
- Send written notices to NJDEP, the municipal governing body, and the municipal clerk.
- Send notices through certified mail with return receipt requested to property owners and residents withina 200-foot radius of the facility, along with qualifying easement holders.
- Post and maintain a visible site notice until the public comment period closes.
- Use additional outreach methods, such as community organizations, flyers, electronic notices, and other communication channels.
- Invite NJDEP, municipal representatives, and local environmental justice organizations to participate.
The hearing must generally take place within the overburdened community on a weekday at or after 6 p.m. Applicants must also provide a virtual participation option and make the hearing recording available online through the end of the public comment period.
The public comment period must remain open for at least 30 days after the hearing and no less than 60 days in total. Throughout this process, applicants should maintain records of notices, publication proofs, mailing receipts, site postings, hearing materials, and submitted comments.
Step 7: Respond to Comments and Await NJDEP’s Decision
After the comment period closes, applicants must submit the hearing transcript, all written comments, and a summary of public feedback, including their responses to the comments, to NJDEP.
Responses should address community concerns and explain proposed solutions. If the responses reveal significant omissions or lead to changes in the project, applicants may need to revise the EJIS and complete additional notification and hearing procedures.
NJDEP then reviews the complete record in accordance with N.J.A.C. 7:1C-9, including the EJIS, supplemental assessments, public testimony, and applicant responses.
The Department determines whether disproportionate impacts can be avoided and whether additional permit conditions are necessary. Depending on the application, NJDEP may deny a new facility if impacts cannot be avoided, unless the project meets the applicable compelling public interest standard. Expansions and major source permit renewals may proceed with conditions addressing environmental and public health stressors.
NJDEP cannot issue its decision until at least 45 days after the public hearing.
Step 8: Maintain Compliance Throughout the Permitting Process
Completing the EJIS does not eliminate a facility’s responsibility to meet environmental requirements. Once NJDEP issues its permitting decision, operators must incorporate any applicable permit conditions into construction plans, operating procedures, and environmental management systems.
These conditions may involve emission limits, monitoring, equipment modifications, traffic controls, and stormwater improvements.
In addition to maintaining records of inspections, monitoring results, maintenance activities, and corrective actions, facilities should assess proposed operational changes to determine if additional permits or environmental reviews are necessary.
A structured NJDEP permit compliance program helps operators track these obligations, demonstrate that approved controls remain effective, and identify potential problems before they lead to enforcement action.
Frequently Asked Questions
- Which facilities are covered by NJDEP’s Environmental Justice Rules?
NJDEP’s Environmental Justice Rules cover specific facility categories and permit applications involving overburdened communities. These include major sources of air pollution, resource recovery facilities, large sewage treatment plants, and certain solid waste facilities that meet the applicable regulatory criteria.
- What is an Environmental Justice Impact Statement (EJIS)?
An EJIS evaluates how a proposed facility or project may affect the surrounding community, including existing environmental conditions, potential impacts, and proposed measures to mitigate adverse effects.
- How long does the NJDEP Environmental Justice review process take?
The review timeline depends on the application and any additional assessments needed. Generally, the process includes a 10-day administrative review period, public notification at least 60 days before the hearing, and a minimum 60-day public comment period.
Preparing for NJDEP Environmental Justice Review
Compliance with New Jersey’s Environmental Justice requirements calls for careful planning, reliable technical assessments, and a thorough understanding of the permitting process. Lockatong Engineering helps regulated facilities navigate these requirements and prepare for NJDEP review.
Our environmental engineering team works closely with facility owners and operators to provide technical guidance, address project-specific challenges, and support informed decisions throughout the application process. Our technical expertise and practical experience help applicants address regulatory requirements and prepare complete, well-supported submissions.
Contact us today at https://lockatong.com/contact-us/ to learn how Lockatong Engineering can support your facility throughout NJDEP’s Environmental Justice review.